NFL plans to avoid Super Bowl power problems of ’13

NFL plans to avoid Super Bowl power problems of ’13

POWER PLAY: The 2013 Super Bowl was delayed for more than a half-hour due to power problems that left much of the stadium in the dark. Photo: Associated Press

EAST RUTHERFORD, N.J. (AP) — With the memory of last February’s Super Bowl power outage front and center, officials have laid out plans for how they plan to avoid a similar problem at MetLife Stadium in February.

The head of Public Service Electric & Gas says the utility is running a third power line into the electrical substation at the Meadowlands sports complex.

PSE&G president Ralph LaRossa said Thursday that even if two of the power lines fail, the third would be enough to power the complex.

LaRossa said the Super Bowl site will require about 18 megawatts of electricity, or about what it takes to power 12,000 homes.

A partial power outage that caused a 34-minute delay at the Superdome was blamed on an electrical relay device installed specifically to prevent a power failure.

Recent Headlines

in Local

Illinois Supremes Back “Home”

illinois supreme court

Illinois Supreme Court Building rehab completed

in Local

Veteran Walks for Others

eric peters

He doesn't carry physical scars from the Iraq and Afghanistan wars, but the wounds are still there

in Local

Judge Threatens Jeff Parsons With Criminal Contempt

Jeff Parsons appears defiant as he walks out of federal court in Springfield July 10, 2014

A federal judge has threatened to hold former THR and Associates boss Jeff Parsons in criminal contempt of court if he doesn't provide the documents needed to proceed with his case.

in Local

Holiday Weekend Means Beefed-up Police Patrols

drunk_driving

Expect a big police presence this Labor Day weekend.

in Local

Tips Sought on Pizza Restaurant Robbery

police_tape

Police are looking for help figuring out who robbed Papa Murphy's late last week.